What will this job actually finish at?
Most jobs are told they are fine until they are not. The number that matters is not what you have spent — it is the rate you have been spending it at, applied to the work that is left.
The number people get wrong
Ask how a job is going and you usually get spend against budget. Sixty per cent spent on a job that is
supposed to be sixty per cent through sounds fine. It is only fine if the job is sixty per cent through.
Spend tells you nothing on its own — it only means something next to physical completion, because
together they give you the rate you have actually been building at. Apply that rate to the work that is left
and you get the real answer, usually earlier than anyone wanted it.
Questions
What is cost to complete?
What it will take from today to finish, based on how the work has actually been running rather than on what was budgeted. Forecast final cost is what you have spent plus that.
Why does percentage complete matter so much?
It converts spend into a rate. If you have spent 60% of the budget to get 40% of the work done, the remaining 60% of work will not come in on the remaining 40% of the money.
Should I count unapproved variations as income?
Prudently, no. Work done and not approved is at risk until it is approved. The tool shows the position both ways so you can see the exposure.
Does this replace a cost report?
No. It is a fast check on whether the job is heading where you think it is. A proper forecast is built from the cost report, the commitments and the programme.
Related free tools
Finding out early is the whole game
Obras keeps the variation register, the cost risk register and the delay record current as the job runs — so the forecast is built on what is actually happening rather than on a number somebody assembled at month end.