Free tool · nothing is uploaded

ITP builder

The hard part of an Inspection and Test Plan is not the table. It is knowing which inspections belong in it, which ones actually stop the work, and what evidence each one has to produce. Pick the work type and it builds the plan — then edit every line of it.

What work is this ITP for?

Hold points are where ITPs go wrong

Most ITP templates hand you an empty grid and leave the hardest decision to you: which of these actually stops the work. Call something a witness point when the contract made it a hold point and you have poured over an uninspected item — which is a demolition conversation, not a paperwork one. Call everything a hold point and the job stops fifteen times a week and people start signing them in batches, which is worse than having none.

Questions

What is the difference between a hold point and a witness point?

A hold point stops the work: it cannot proceed past that step until the nominated party has inspected and signed. A witness point means the party is notified and may attend, but work can continue if they do not. Getting these the wrong way round is the most common ITP mistake, and it is usually found at the worst moment.

Are these the right hold points for my job?

They are the ones commonly applied to this work type. Your contract and specification win. What is a hold point on one project is a witness point on another, and the principal contractor or superintendent may nominate their own. Always reconcile against the project specification before issuing.

Is an ITP a safety document?

No. An ITP is a quality and contract document. It records what gets inspected, by whom and against what. It is not a SWMS and it does not manage safety risk — you need both.

Can I edit the rows?

Yes. Every row can be edited, and you can add or delete rows. It is a starting point, not a finished document.

Does anything get uploaded?

No. Everything stays in your browser on your device. Print or save the PDF before you close the tab.

Related free tools

Pour readinessIs the pre-pour hold point actually closed? Floor readinessThe whole deck before you book concrete. What is blocking my job?Ten activities, and what stops each one. Defects QRWhat the ITP finds has to go somewhere.

An ITP on paper is a plan. An ITP that stops work is a control.

In Obras every hold point carries a QR band. Scan it on the deck and the live record says whether it is open or closed — so an open hold point blocks the pour instead of being discovered afterwards.

See Obras in action Take a free SWMS

This is a practical site-management tool. It is not legal, engineering or regulatory advice and does not guarantee compliance or a satisfactory inspection outcome. Requirements may vary by jurisdiction, project, contract and circumstances.

Want a person to look at it?

The tools above are free and yours to use. When you need the paperwork behind them reviewed by someone who has run sites, Obras HSE Services is a live consulting business in south-east Queensland.